The Commission does not have delegated review for water or sewer. In order to receive a SCDHEC Permit to Construct the following items must be submitted to the Commission’s Staff Engineer, Guy Schmoltze, P.E. through the Project Portal:
Once the above items have been received and approved by the Commission’s Staff Engineer and the required tap fees have been paid, a letter will be written to SCDHEC in order to obtain a SCDHEC Construction Permit.
In order to receive a SCDHEC Permit to Operate the following Items must be completed: